Curtailment is the part of hosted mining that buyers understand last. The economics are discussed constantly — how much a site earns by powering down, how demand response pays. What gets far less attention is the contract language that decides who absorbs the loss when the power stops, and whether the event counts as curtailment at all.
That distinction is not academic. Two sites can curtail for the same number of hours in the same month and produce completely different outcomes for the miner, purely because of how their agreements are written.
Curtailment and force majeure are not the same thing
Most hosting agreements treat these as separate categories, and the difference matters.
Curtailment is usually defined as a planned or contractually anticipated reduction in power, whether that is economic curtailment when prices spike, a demand response event the host has enrolled in, or a utility instruction under an interruptible rate. It is foreseeable. The agreement normally sets out what happens: whether hosting fees pause, whether the miner shares in any demand response revenue, and whether there is an annual cap on curtailed hours.
Force majeure covers events outside either party’s reasonable control — severe weather, grid failure, regulatory action, and in many agreements a broad catch-all. Its legal function is different. Force majeure typically excuses the host from performing, which means it may suspend obligations without triggering any of the remedies a curtailment clause would provide.
The practical risk is that an event gets classified under whichever heading is more favourable to the host. A multi-day outage described as force majeure may carry no fee relief and no service credit. The same outage described as curtailment might pause billing. A buyer who has read only the curtailment section has read half the contract.
The questions that determine who bears the loss
Do hosting fees continue during curtailment?
This is the single most consequential term and it varies widely. Some agreements pause the power component while continuing a fixed infrastructure or rack fee. Some pause everything. Some continue billing in full on the basis that the host’s own costs continue regardless.
None of these is inherently unfair — a host carrying fixed infrastructure costs has a legitimate argument — but the miner needs to know which model applies before signing, because it changes the effective cost per kilowatt-hour in any month with meaningful curtailment.
Is there a cap on curtailed hours?
An agreement that permits unlimited curtailment at the host’s discretion is not really a hosting agreement with a defined service level. Look for an annual or monthly cap, and for what happens when it is exceeded: fee relief, service credits, or a termination right.
Uncapped curtailment combined with continued billing is the combination worth scrutinising hardest.
Who receives demand response revenue?
Where a site is enrolled in a grid programme, curtailment can generate payments. The agreement should state plainly whether those payments are retained by the host, shared, or passed through, and on what basis they are calculated. Silence here generally means the host keeps them.
This is a reasonable commercial position if it is stated. The problem is when a miner assumes a share they were never promised. Our discussion of curtailment revenue in ERCOT covers how these programmes pay; the contract determines who the payment reaches.
How is notice handled?
Economic curtailment can sometimes be anticipated. Emergency curtailment cannot. Where notice is required, check the window and the method, and check whether the obligation survives an emergency. A notice provision that is waived whenever the host declares an emergency provides less protection than it appears to.
Reading the force majeure clause properly
Three features are worth checking in any force majeure provision.
The list, and whether it is exhaustive. A closed list of named events is more predictable than an open list ending in general catch-all language. Broad catch-alls tend to favour the party relying on them.
Whether grid instability is named. For a mining host, grid events are foreseeable and in some markets routine. A force majeure clause that expressly includes general grid conditions converts an ordinary operating risk into an excuse for non-performance. That is a significant reallocation of risk and is worth negotiating.
What happens if it persists. Good drafting gives either party a termination right once a force majeure event continues beyond a defined period, along with terms for returning hardware. Without it, a miner can be left with equipment at a site that is not producing and not billing, with no exit.
Where this intersects with everything else
Curtailment terms do not sit in isolation. They interact with uptime guarantees, with insurance, and with what happens if the host fails.
An uptime SLA that excludes curtailment from its calculation is common and often reasonable, but it means the headline uptime figure is not a measure of how much the machines actually ran. Ask how uptime is defined and what is excluded.
Business interruption cover generally responds to physical damage, not to a commercial decision to power down. Curtailment losses are usually a contractual matter rather than an insured one — our guide to mining insurance coverage sets out what these policies typically do and do not reach.
And if a prolonged force majeure period leads to insolvency rather than recovery, the questions shift to ownership and recovery of hardware, which we cover in where your miners sit legally when a host goes bankrupt.
Economic curtailment and reliability curtailment behave differently
Agreements that handle this well distinguish between two causes, because the fairness of each arrangement depends on which one is operating.
Economic curtailment happens when power prices rise above the point where running is profitable, or where a demand response payment exceeds mining revenue. It is a commercial decision. Somebody is better off because the machines stopped, and the question is simply whether that benefit reaches the miner whose machines were stopped.
Reliability curtailment happens when the grid operator or utility requires load reduction to maintain system stability. Nobody profits; the power is simply unavailable. The fairness question here is different — it is about who absorbs an unavoidable loss, not who shares an avoidable gain.
An agreement that treats both identically is usually written in the host’s favour, because the economic case is where the upside sits. If your contract pauses fees during reliability events but continues them during economic curtailment, you are paying to be switched off so that someone else can capture the spread. That may still be an acceptable deal at the right price, but it should be a decision rather than a discovery.
Interruptible rates change the baseline
Many mining sites buy power on an interruptible or curtailable tariff. The electricity is cheaper precisely because the utility retains the right to reduce supply, and that right is what makes the headline rate achievable.
This is worth understanding because it reframes the conversation. Curtailment on such a site is not a failure of the arrangement; it is the arrangement. A host quoting an unusually low rate while describing curtailment as rare is describing two things that do not normally coexist.
The useful questions are how many interruptible hours the tariff permits, how many were actually called in the last twelve months, and whether that history is available. Past hours are not a guarantee of future ones, but a host who can answer is operating with better records than one who cannot.
A short review list
- Are curtailment and force majeure defined separately, and is it clear which governs a given event?
- Do hosting fees pause, reduce, or continue during curtailment, and which components?
- Is there a cap on curtailed hours, and what remedy applies once it is exceeded?
- Who receives demand response or curtailment programme revenue?
- What notice is required, and does it survive an emergency?
- Does the force majeure list include general grid conditions?
- Is there a termination right if force majeure persists, and terms for hardware return?
- Does the uptime SLA exclude curtailed hours from its calculation?
None of these questions requires a lawyer to ask. They do require reading the agreement as a whole rather than the section with the most attractive number in it. A host willing to answer all eight plainly is telling you something useful about how they operate.
For a broader checklist before signing, see our guide to evaluating a colocation provider.
Explore Rax Mining
- Bitcoin Miner Hosting — Tiered rates from $0.085/kWh, NatGas from $0.055/kWh
- NatGas MDU Units — 1MW modular datacenter containers
- Mining Profitability Calculator — Estimate your mining returns
- Our Facility — Tour our mining infrastructure